Example SWMS

The switchboard upgrade SWMS template, as the crew and the builder see it.

An example with made-up details. Yours fill in from the job, with your business, licence and logo.

Safe Work Method Statement

Switchboard upgrade or replacement

SWMS-0007 · Revision 1 · Example Electrical

Site
12 Example Street, Southport QLD 4215
Work starts
8 Oct 2026
Principal contractor
None
Prepared by
Sam Sparky
Contact
0400 000 000 · hello@example.com
Last updated
8 Oct 2026, 7:00 am

High risk construction work

  • Likely to disturb asbestos
  • On or near energised electrical installations or services

Steps, hazards and controls

  1. 1. Arrange the supply disconnection and tell the customer

    Hazards: Working on a board that can't be fully isolated on site (service fuse or mains still live), loss of supply to medical or critical equipment. High

    Controls: Arrange a network disconnection. Only pull the service fuse if the network authorises you to (rules differ by state), wearing arc-rated PPE. Confirm with the customer that no one relies on life-support equipment, and agree the outage time. Medium

    Who: Licensed electrician in charge

  2. 2. Check the old board for asbestos

    Hazards: Asbestos in older board backing panels (often pre-1990). High

    Controls: Treat old board backing as asbestos unless known otherwise. Don't drill, cut or break it. Remove and dispose of it only as the asbestos rules allow (licensed removalist where required). Low

    Who: Licensed electrician in charge

  3. 3. Isolate and prove dead

    Hazards: Electric shock, arc flash from consumer mains or a second supply (solar, battery, generator). High

    Controls: Identify the circuit/s. Isolate at the switchboard, plus any other supply (solar inverter, battery, generator), lock off and tag (personal lock and danger tag). Prove the tester on a known live source, test for dead at the point of work, then prove the tester again. Check for shared or borrowed neutrals. Treat everything as live until tested. Isolate solar inverters, batteries and any other supply too, and test the consumer mains. Low

    Who: Licensed electrician in charge

  4. 4. Remove the old board and fit the new one

    Hazards: Manual handling, cuts, mixing up circuits, loose connections. Medium

    Controls: Label every circuit before disconnecting. Two people for heavy enclosures. Torque connections as the manufacturer says. Low

    Who: All workers

  5. 5. Test, re-energise and hand over

    Hazards: Faults on re-energising, incorrect polarity, RCDs not working. High

    Controls: Do all the required tests before re-energising, then earth fault-loop impedance and RCD trip times. Remove locks and tags only when the work is complete and tested. Restore the supply as the network requires. Give the customer the certificate. Low

    Who: Licensed electrician in charge

PPE

Safety boots, Safety glasses, Insulated gloves (rated), Arc-rated clothing, Arc-rated face shield, P2 mask

Plant and equipment

Insulated hand tools, voltage tester (CAT IV), insulation resistance tester, loop impedance tester, lock-out kit, barriers and signs.

Emergency

Call 000 for an ambulance. First aid kit and fire extinguisher in the vehicle. Electric shock: don't touch the person until the supply is off, then call 000 and start CPR if needed. Anyone who gets a shock sees a doctor even if they seem fine, and the shock is reported to the electrical safety regulator. Nearest hospital: (add for this site).

Workers signed on to revision 1

By signing, each worker confirms this SWMS was explained to them, they understand it, and they will follow it.